Site and equipment placement
Placement must account for manufacturer clearances, property lines, openings, exhaust, combustion air, noise, service access, snow, drainage, flooding, vegetation, and local requirements. A stable, level base is also required.
Automatic transfer switch
The ATS detects an outage, disconnects the building from utility power, and connects the generator. Its rating, service-entrance suitability, switching arrangement, and load-management capabilities must match the electrical design.
Gas-line planning
A licensed gas professional assesses connected demand, pressure, meter and regulator capacity, pipe sizing, routing, protection, bonding, and utility coordination. Never assume an existing gas line has spare capacity.
Permits and commissioning
Requirements vary by province, territory, and municipality. The project may involve gas and electrical permits, utility review, inspections, and local placement or noise rules. Gas and electrical work must be completed by appropriately licensed professionals.